Home » Small Modular Reactors and Microreactors Timeline: From 2022 to 2027

Small Modular Reactors and Microreactors Timeline: From 2022 to 2027

Quick take: Small modular reactors (SMRs) and microreactors went from the first NRC design certification vote in 2022 to a run of US construction permits in 2026: TerraPower’s Natrium plant in March, TVA’s Clinch River BWRX-300 in September and X-energy’s Long Mott plant for Dow in November. A construction permit does not authorize operation, and most investment decisions and operating dates are still ahead. Newest and upcoming dates are at the top. This page was last reviewed on November 25, 2026.

Timeline (latest first)

WhenWhat happenedStatusSource
2027Dow expects a preliminary investment decision on Long Mott in 2027, according to World Nuclear News. Dow has not made a final construction decision.ExpectedWorld Nuclear News, our Long Mott report
December 2026The NRC’s draft safety evaluation report on Holtec’s limited work authorization request for Palisades is anticipated, according to World Nuclear News.ExpectedWorld Nuclear News, our Palisades report
November 9, 2026The NRC issues a construction permit for X-energy’s Long Mott plant (four Xe-100 units) at Dow’s Seadrift site in Texas. The NRC calls it the first high-temperature gas-cooled reactor construction permit in nearly 60 years. The permit does not authorize operation.DoneNRC release 26-083, our report on the safety review
October 22, 2026World Nuclear News reports that the Navy selected Radiant’s 1 MW Kaleidos microreactor for Naval Weapons Station Crane in Indiana, under the Janus Program. Radiant is still testing the reactor at Idaho National Laboratory’s DOME facility, and no deployment date has been announced.Done (selection)World Nuclear News, our report
October 2, 2026Holtec reports that it submitted the preliminary safety analysis report for two SMR-300 units at Palisades, Michigan, completing the second part of its construction permit application. This is company-reported; the date is that of the World Nuclear News article.Done (company-reported)World Nuclear News, our report
September 29, 2026The NRC approves a construction permit for TVA’s Clinch River SMR, a 300 MW GE Vernova Hitachi BWRX-300. The NRC says the review took 14 months, four months ahead of schedule. World Nuclear News dates the news September 30.DoneNRC release 26-079, our report
July 4, 2026Aalo Atomics reports that its Aalo-X test reactor at Idaho National Laboratory reached zero-power criticality at 12:20 a.m. MT. DOE calls it the fourth DOE-authorized reactor to reach criticality, against a goal of three by July 4.Done (company-reported)ANS, DOE
March 4, 2026The NRC approves TerraPower’s construction permit for Natrium Kemmerer Unit 1 in Wyoming. An operating license is still needed.DoneANS
May 29, 2025The NRC grants standard design approval to NuScale’s US460 design: 77 MWe per module, up to six modules.DoneNRC release 25-033
April 2025The Canadian Nuclear Safety Commission approves a licence for Ontario Power Generation to construct a BWRX-300 at Darlington, the first of four planned units. It does not permit operation.DoneWorld Nuclear News
July 2024The ADVANCE Act becomes law. It directs the NRC to speed licensing and lowers fees for advanced reactor applicants.DoneNRC, World Nuclear News
December 2023NRC commissioners vote to approve Kairos Power’s Hermes construction permit in Oak Ridge, Tennessee, a 35 MWt demonstration reactor. DOE calls it the first Gen IV construction permit.DoneDOE Office of Nuclear Energy
July 29, 2022The NRC Commission votes to certify NuScale’s 50 MWe-per-module design, the first SMR design the NRC certified. The final rule took effect February 21, 2023.DoneDOE Office of Nuclear Energy

What the timeline tells you

Regulators are moving faster than before: the NRC says Clinch River took 14 months, four months ahead of schedule. But permits and approvals are not power plants. Every 2026 permit above lets construction begin and none authorizes operation. Dow has made no final construction decision on Long Mott, and the Navy has announced no deployment date for Kaleidos. Treat company-reported test results, such as Aalo’s criticality, as milestones for test reactors rather than commercial plants.

Related reading

Dates marked “expected” or “scheduled” are plans, not results. This page will be reviewed quarterly.