Quick take: Small modular reactors (SMRs) and microreactors went from the first NRC design certification vote in 2022 to a run of US construction permits in 2026: TerraPower’s Natrium plant in March, TVA’s Clinch River BWRX-300 in September and X-energy’s Long Mott plant for Dow in November. A construction permit does not authorize operation, and most investment decisions and operating dates are still ahead. Newest and upcoming dates are at the top. This page was last reviewed on November 25, 2026.
Timeline (latest first)
| When | What happened | Status | Source |
|---|---|---|---|
| 2027 | Dow expects a preliminary investment decision on Long Mott in 2027, according to World Nuclear News. Dow has not made a final construction decision. | Expected | World Nuclear News, our Long Mott report |
| December 2026 | The NRC’s draft safety evaluation report on Holtec’s limited work authorization request for Palisades is anticipated, according to World Nuclear News. | Expected | World Nuclear News, our Palisades report |
| November 9, 2026 | The NRC issues a construction permit for X-energy’s Long Mott plant (four Xe-100 units) at Dow’s Seadrift site in Texas. The NRC calls it the first high-temperature gas-cooled reactor construction permit in nearly 60 years. The permit does not authorize operation. | Done | NRC release 26-083, our report on the safety review |
| October 22, 2026 | World Nuclear News reports that the Navy selected Radiant’s 1 MW Kaleidos microreactor for Naval Weapons Station Crane in Indiana, under the Janus Program. Radiant is still testing the reactor at Idaho National Laboratory’s DOME facility, and no deployment date has been announced. | Done (selection) | World Nuclear News, our report |
| October 2, 2026 | Holtec reports that it submitted the preliminary safety analysis report for two SMR-300 units at Palisades, Michigan, completing the second part of its construction permit application. This is company-reported; the date is that of the World Nuclear News article. | Done (company-reported) | World Nuclear News, our report |
| September 29, 2026 | The NRC approves a construction permit for TVA’s Clinch River SMR, a 300 MW GE Vernova Hitachi BWRX-300. The NRC says the review took 14 months, four months ahead of schedule. World Nuclear News dates the news September 30. | Done | NRC release 26-079, our report |
| July 4, 2026 | Aalo Atomics reports that its Aalo-X test reactor at Idaho National Laboratory reached zero-power criticality at 12:20 a.m. MT. DOE calls it the fourth DOE-authorized reactor to reach criticality, against a goal of three by July 4. | Done (company-reported) | ANS, DOE |
| March 4, 2026 | The NRC approves TerraPower’s construction permit for Natrium Kemmerer Unit 1 in Wyoming. An operating license is still needed. | Done | ANS |
| May 29, 2025 | The NRC grants standard design approval to NuScale’s US460 design: 77 MWe per module, up to six modules. | Done | NRC release 25-033 |
| April 2025 | The Canadian Nuclear Safety Commission approves a licence for Ontario Power Generation to construct a BWRX-300 at Darlington, the first of four planned units. It does not permit operation. | Done | World Nuclear News |
| July 2024 | The ADVANCE Act becomes law. It directs the NRC to speed licensing and lowers fees for advanced reactor applicants. | Done | NRC, World Nuclear News |
| December 2023 | NRC commissioners vote to approve Kairos Power’s Hermes construction permit in Oak Ridge, Tennessee, a 35 MWt demonstration reactor. DOE calls it the first Gen IV construction permit. | Done | DOE Office of Nuclear Energy |
| July 29, 2022 | The NRC Commission votes to certify NuScale’s 50 MWe-per-module design, the first SMR design the NRC certified. The final rule took effect February 21, 2023. | Done | DOE Office of Nuclear Energy |
What the timeline tells you
Regulators are moving faster than before: the NRC says Clinch River took 14 months, four months ahead of schedule. But permits and approvals are not power plants. Every 2026 permit above lets construction begin and none authorizes operation. Dow has made no final construction decision on Long Mott, and the Navy has announced no deployment date for Kaleidos. Treat company-reported test results, such as Aalo’s criticality, as milestones for test reactors rather than commercial plants.
Related reading
- X-energy’s Long Mott Reactor Clears a Major Texas Safety Review
- NRC Issues Clinch River BWRX-300 Construction Permit
- Navy Picks Radiant’s Kaleidos Microreactor for an Indiana Base
- Holtec Files Safety Report for Two SMR-300s at Palisades
- Last Energy’s PWR-5 Pilot Reactor Clears DOE Safety Analysis
Dates marked “expected” or “scheduled” are plans, not results. This page will be reviewed quarterly.