Home » Nuclear Fission » Last Energy’s PWR-5 Pilot Reactor Clears DOE Safety Analysis

Last Energy’s PWR-5 Pilot Reactor Clears DOE Safety Analysis

The U.S. Department of Energy approved the Documented Safety Analysis for Last Energy’s PWR-5 pilot reactor at Texas A&M’s RELLIS campus. A readiness review still stands between the project and…

A worker operating a machine on a factory floor, illustrating factory-based manufacturing of modular equipment

The U.S. Department of Energy (DOE) has approved the Documented Safety Analysis (DSA) for the PWR-5, a pilot reactor that Last Energy is building at the Texas A&M RELLIS campus in Bryan, Texas. World Nuclear News reported the approval on October 8, 2026.

Timeline: Small Modular Reactors and Microreactors

  • 2027 (expected): Dow’s preliminary investment decision on Long Mott
  • December 2026 (expected): NRC draft safety report on Holtec’s Palisades work authorization
  • Nov. 9, 2026: NRC issues Long Mott construction permit
  • Sept. 29, 2026: NRC approves Clinch River BWRX-300 permit

See the full Small Modular Reactors and Microreactors timeline

The quick take

  • DOE accepted the safety analysis. Project reporting describes the DSA as the final safety analysis in DOE’s authorization process.
  • A readiness review is next, with no published date.
  • The reactor has not reached criticality and is not yet authorized to operate.
  • The PWR-5 is a 5 megawatt-electric pilot, not the commercial design.

What the DSA approval covers

A DSA documents the safety basis for a DOE-authorized facility: the hazards, the controls, and how the plant is meant to respond to accidents. It builds on the Preliminary DSA (PDSA), which DOE approved in May 2026, according to Last Energy’s May 28 announcement. Last Energy was selected for DOE’s Reactor Pilot Program in August 2025.

World Nuclear News describes the readiness review as the final step before authorization for criticality and reactor operations. In its May announcement, Last Energy said DOE authorization would let it bring fuel on site, achieve criticality and operate the reactor. The company also said the fuel had already been manufactured and that construction of the reactor building was nearing completion. So this is a safety-basis approval, not permission to run the reactor.

“PDSA approval is a major step in moving the PWR-5 from construction into operations,” said Adam Lenarz, Last Energy’s vice president of development, after the May approval.

What the PWR-5 is

The PWR-5 is a pilot version of Last Energy’s commercial PWR-20. Last Energy says it uses the same physical geometry as the PWR-20 but with reduced fuel enrichment, scaled for 5 megawatts of electrical output. The PWR-20 is a 20 megawatt-electric plant based on pressurized water reactor technology and standard low-enriched uranium fuel. World Nuclear News says it sits in a 1,000-tonne, hermetically sealed steel structure. Last Energy plans to build such units in a factory and ship them to site, and says the pilot will demonstrate low-power criticality first, then progress to generating electricity.

The Reactor Pilot Program was created under Executive Order 14301. DOE describes it as a pathway to demonstrate advanced reactors and speed later commercial licensing. Its stated goal was criticality for at least three advanced reactor concepts outside national laboratories by July 4, 2026. The PWR-5 has not yet reached criticality. Commercial plants remain under the Nuclear Regulatory Commission, not DOE.

Why It Matters to You

This is a test reactor, so it won’t power anyone’s home. The reactor sits on the RELLIS campus, part of the Texas A&M University System’s energy proving grounds initiative, which lists workforce development among its purposes. If the pilot works, it is meant to show whether small factory-built reactors can be licensed faster, and that would matter most to future customers of commercial units. None of that has happened yet, and no source here ties the approval to household power bills.

What the approval doesn’t show

  • DOE accepted the safety analysis on paper. The reactor has not operated, and criticality and power generation have not happened.
  • The readiness review is still ahead and no timeline is published, so any “within months” estimate is a guess.
  • The 20 MWe PWR-20 is a separate commercial design that has not been built or licensed in the United States.
  • The DSA was approved by DOE under its own process. It does not replace NRC licensing for a commercial plant.

Quick answers

Can the PWR-5 start up now?

No. DOE still has to complete the readiness review and authorize fuel loading, criticality and operation.

Who regulates this reactor?

DOE, through its authorization process for the Reactor Pilot Program. Commercial plants stay under the NRC.

Why is the project at Texas A&M?

The reactor sits on the RELLIS campus, part of the Texas A&M University System’s energy proving grounds initiative. Last Energy holds a land lease there.