On October 2, 2026, Holtec International filed the second part of its construction permit application for two small modular reactors at the Palisades Energy Center in Covert Township, Michigan. The units, called Pioneer 1 and 2, would sit next to the older Palisades reactor that Holtec is trying to restart. That restart is paused after a fuel assembly tipped during loading.
- 2027 (expected): Dow’s preliminary investment decision on Long Mott
- December 2026 (expected): NRC draft safety report on Holtec’s Palisades work authorization
- Nov. 9, 2026: NRC issues Long Mott construction permit
- Sept. 29, 2026: NRC approves Clinch River BWRX-300 permit
See the full Small Modular Reactors and Microreactors timeline
- Size: two SMR-300 units, about 300 megawatts of electricity each, roughly 600 megawatts for the plant (Holtec’s description)
- Cost: no full-plant estimate published; Holtec says the full cost is still undetermined
- Target: online in the early 2030s, which is Holtec’s goal
- Status: PSAR filed October 2, 2026; no NRC construction permit yet
What Holtec filed and what comes next
The new document is a Preliminary Safety Analysis Report, or PSAR. It describes the plant design and the safety case that NRC staff will review before they decide whether to issue a construction permit. World Nuclear News says the PSAR completes the second phase of the construction permit application. Holtec called it “the most significant step to date toward establishing the regulatory framework for the Pioneer plant.”
The road here has been steady. Holtec filed a limited work authorization request and Environmental Report in December 2025, and the NRC accepted and docketed the limited work authorization application in February 2026. On August 28, 2026, the NRC granted an exemption for permanent support-of-excavation and cutoff-wall systems at the site. The NRC’s draft safety evaluation report for the limited work authorization is expected in December 2026.
A filing is not an approval, though. Holtec still needs an NRC safety evaluation and environmental assessment, and it must file a separate operating license application. Its own next steps include a construction cost estimate, a construction simulation, and confirmatory safety analyses. The schedule depends on how review goes.
Why build at an existing site
Holtec plans to share the existing switchyard and radiation protection systems with the older reactor, according to a March 2025 Latitude Media report. That avoids building some new infrastructure. It does not remove the need for a full NRC review of the new units. Holtec also told Latitude Media that it believes it controls about 75 percent of the supply chain for its reactors. That is a company belief, and there is no independent check of it.
The US Department of Energy selected Holtec in December 2025 for up to $400 million in cost-shared federal funding for the Palisades SMR project. The figure is a ceiling, not a payment already made, and the split between federal and private money isn’t public in the sources reviewed.
How the SMR-300 is designed to stay safe
The NRC’s design page describes the SMR-300 as a passively safe pressurized light water plant. In normal operation it uses forced circulation, with reactor coolant pumps, to reach rated power. Its safety systems are gravity-driven and, the NRC page says, do not need pumps, outside water, outside power, or operator action. The annular water reservoir between the containment and the containment enclosure serves as the ultimate heat sink.
Holtec says the core sits deep underground in a steel and concrete enclosure, and that it plans factory-built modules and robotic welding. Those manufacturing points are Holtec’s claims, and no independent data backs them yet.
Why It Matters to You
For most readers there is no direct benefit yet. Nothing here is built, and no permit has been issued. If the NRC approves the plant and construction goes as Holtec hopes, Pioneer 1 and 2 could add about 600 megawatts of electricity in Michigan in the early 2030s. Whether that power would lower anyone’s electric rates is not addressed in any source reviewed, so nobody should count on cheaper bills. People who live near Covert Township and the workers and suppliers tied to the project would feel any change first.
Open questions
- Will the NRC issue a construction permit, and on what timeline?
- What will the full plant cost? Holtec says it is still undetermined.
- How is the $400 million DOE award, which is up to that amount and cost-shared, split between federal and private money?
- Do Holtec’s supply chain and factory-building claims hold up under independent review?
Quick answers
What is a Preliminary Safety Analysis Report?
It is the design and safety document an applicant submits as part of a construction permit application. NRC staff review it to decide whether the plant can be built safely at the site.
When could the reactors operate?
Holtec targets the early 2030s. That depends on NRC permits, an operating license, and construction. Holtec describes each SMR-300 as about 300 megawatts of electricity and the two-unit plant as roughly 600 megawatts.
Does this depend on the Palisades restart?
They are separate projects at the same site. The SMR application is on its own NRC schedule, though both share the property and some infrastructure.
Sources
- World Nuclear News: Second part of construction permit application submitted for SMRs at Palisades (Oct 2, 2026)
- US NRC: SMR-300 (SMR, LLC, a Holtec International company) (accessed Oct 13, 2026)
- Holtec International: SMR-300 (accessed Oct 13, 2026)
- ANS Nuclear Newswire: DOE selects TVA and Holtec for SMR awards (Dec 3, 2025)
- Latitude Media: What will it take for Holtec to put small nuclear reactors at Palisades? (Mar 12, 2025)
