Quick take: Vogtle Units 3 and 4 finished in 2023 and 2024, and the focus has since moved to restarting shut reactors, upgrading running ones and finishing overseas builds. Palisades began fuel loading on August 30, 2026 but is stalled after a fuel assembly tilted. Crane (formerly Three Mile Island Unit 1) is targeted for 2027 by its owner, and Duane Arnold for early 2029. Newest and upcoming dates are at the top. This page was last reviewed on November 25, 2026.
Timeline (latest first)
| When | What happened | Status | Source |
|---|---|---|---|
| 2030 | EDF says Hinkley Point C Unit 1 in the UK is organized around becoming operational in 2030, as quoted by Engineering News from an EDF update dated February 20, 2026. | Expected (company-reported) | Engineering News |
| First quarter of 2029 | NextEra and Google say Duane Arnold in Iowa will be online by the first quarter of 2029, pending regulatory approvals. The plant stopped operating in 2020. The deal was announced October 27, 2025. | Expected (company-reported) | NextEra release, World Nuclear News |
| 2028 | Constellation says the first of its 890 MW of Google-backed uprates is expected by 2028. | Expected (company-reported) | Constellation release, our report |
| 2027 | Constellation says Crane in Pennsylvania will return 835 MW to the grid in 2027, moved up from 2028. Its CEO said on April 1, 2026 that interconnection “could be delayed into the 2030s.” | Expected (company-reported) | World Nuclear News, Sept. 28, 2026, World Nuclear News, Apr. 1, 2026, our report |
| October 13, 2026 | The NRC issues a one-time amendment, under exigent circumstances, letting Holtec remove a tilted fuel assembly at Palisades by an alternate method. Fuel loading and some restart work are stalled, and restart has no firm date. | Done (restart pending) | ANS, our report |
| October 6, 2026 | Google and Constellation announce 890 MW of new capacity through uprates at 11 Constellation units in Illinois, Pennsylvania and New Jersey. | Done (deal) | Constellation release, our report |
| September 21, 2026 | Mochovce 4 in Slovakia begins power generation at 15:33 local time. The operator calls it the last major stage before the unit is put into operation. | Done | World Nuclear News, our report |
| September 18, 2026 | The NRC issues the final environmental assessment and finding of no significant impact for the Crane restart. Licensing actions are still under review, and the plant is not yet authorized to resume power operations. | Done (licensing pending) | World Nuclear News, NRC |
| August 30, 2026 | Palisades in Michigan enters Mode 6 and begins fuel loading. One previously used assembly then tilts in the vessel. The plant was reconnected to the 345-kV switchyard on September 11. | Done | ANS, our report |
| January 2026 | The NRC approves license amendments for Limerick’s Digital Modernization Project, replacing analog safety systems with a digital plant protection system. The NRC calls Limerick the first operating US plant authorized for such a retrofit. | Done (approval) | World Nuclear News, our report |
| December 14, 2025 | EDF reports that Flamanville 3 in France reached 100% nuclear thermal power for the first time, at 11:37 a.m. | Done (company-reported) | EDF, ANS |
| July 24, 2025 | The NRC approves the regulatory package for restarting Palisades. The exemption takes effect August 25, 2025, when Holtec plans to move to its power-operations licensing basis. | Done | World Nuclear News |
| April 29, 2024 | Georgia Power declares Vogtle Unit 4 in commercial operation. | Done | Southern Company |
| July 31, 2023 | Vogtle Unit 3 enters commercial operation, according to Southern Company’s later release on Unit 4. | Done | Southern Company |
What the timeline tells you
Restarts are slower than announcements suggest. Palisades had a reconnection target of end of February 2026 that was missed, and as of the latest reports it has no firm restart date. Crane’s 2027 date is the owner’s target, the NRC says the plant is not yet authorized to resume power operations, and the company’s own CEO has warned interconnection could slip. Uprates and digital upgrades add capacity without new sites, but most of their dates are still company expectations.
Related reading
- Palisades Fuel Loading Paused After a Fuel Assembly Tipped
- Crane Nuclear Restart in Middletown, PA Now Ahead of Schedule
- Google and Constellation Back 890 MW of Reactor Uprates
- Mochovce 4 Begins Power Generation in Slovakia
- Limerick Gets NRC Approval for Digital Safety Controls
Dates marked “expected” or “scheduled” are plans, not results. This page will be reviewed quarterly.