At the Crane Clean Energy Center in Middletown, Pennsylvania, fresh fuel assemblies and new transformers already sit on site, waiting for a reactor that hasn’t produced power since 2019. On November 9, Constellation Energy chairman, president and CEO Joe Dominguez told investors the restart of the plant, formerly Three Mile Island Unit 1, remains on track for the second half of 2027. That would put it ahead of the company’s own earlier schedule. Nuclear Newswire reported his comments three days later, after Constellation’s third quarter earnings call.
- Q1 2029 (expected, company-reported): Duane Arnold back online
- 2027 (expected, company-reported): Crane returns 835 MW
- Oct. 13, 2026: NRC allows alternate removal of tilted Palisades fuel assembly
- Sept. 21, 2026: Mochovce 4 begins power generation
What Dominguez Told Investors
The Crane update was one line among several on a call that also covered new nuclear uprate deals and a previously announced capacity expansion with Google. Dominguez called a regulatory decision from September “favorable” and said fuel assemblies and transformers are already on site at Crane. Neither detail means the reactor can run yet. It means two of the physical pieces needed for restart have arrived at the plant, and that the company still believes its timeline will hold.
Crane is not a new reactor. It is Constellation’s attempt to bring an existing, previously profitable plant back from a shutdown that happened for economic reasons, not safety ones. If the timeline holds, it would be only the second time a U.S. commercial reactor has returned to service after being retired for decommissioning.
Crane Clean Energy Center at a Glance
| Detail | Figure |
|---|---|
| Formerly | Three Mile Island Unit 1 |
| Location | Londonderry Township, near Middletown, Pennsylvania |
| Capacity | 835 MW |
| Shut down | 2019, for economic reasons |
| Restart financing | $1 billion DOE loan, closed November 2025 |
| Anchor customer | Microsoft, 20-year power deal signed 2024 |
| Permanent operating jobs | About 627 |
| Target restart | Second half of 2027 |
Source: U.S. Department of Energy, Office of Energy Dominance Financing; Constellation Energy; Microsoft.
The Regulatory Clock So Far
- June 9, 2026: The NRC released a draft environmental assessment finding no significant impact from the restart, then opened it for public comment.
- September 25, 2026: The NRC made that finding official in the Federal Register once the comment period closed. That step lets Constellation skip a longer environmental impact statement, saving significant review time.
- The NRC is now running safety reviews and on-site inspections of restart work at the plant, in parallel with the environmental track.
- A final decision on the restart request itself, separate from the environmental finding, is expected sometime in 2027, according to the NRC’s own June announcement.
What’s Not Decided Yet
- The NRC hasn’t issued its final restart decision. That approval, not the environmental finding, is what actually lets Crane load fuel and run.
- “On track” and “ahead of schedule” are Constellation’s own words from an earnings call, not a regulatory guarantee.
- There’s no specific restart date yet, only a six-month window: the second half of 2027.
- Fuel assemblies and transformers being on site means the parts have arrived, not that they’re installed or licensed for use.
Why It Matters to You
- Most of Crane’s power is already spoken for. Microsoft’s 20-year agreement, signed in 2024, is built to match its own data center energy use within the 13-state PJM grid, not to lower anyone’s home electric bill directly.
- Even so, 835 MW of restarted, carbon-free baseload adds supply to that same regional grid, which covers Pennsylvania and a dozen other states plus Washington, D.C.
- Two different job figures are floating around, from two different years. A 2024 economic-impact study for Pennsylvania’s building trades projected roughly 3,400 direct and indirect construction jobs, $16 billion in state GDP and more than $3 billion in state and federal taxes. The Department of Energy’s own October 2026 figures put permanent operating jobs at about 627 once the plant is actually running. Neither number has turned into a paycheck yet.
- If 2027 holds, Crane becomes a working example other utilities with retired plants can point to, proof that restarting is a real option next to building new.
Parts on a loading dock are not power on the grid. Until the NRC signs off on the restart itself, that’s all Crane has: components, a plan, and a timeline Constellation insists is still holding.
Sources
- Constellation Energy: Constellation Reports Third Quarter 2026 Results (Nov. 9, 2026)
- Nuclear Newswire: Constellation Q3 updates: New Peak+, uprates, restart, midterm elections (Nov. 12, 2026)
- Nuclear Newswire: NRC roundup: Crane EA/FONSI; new Agreement State (Sept. 29, 2026)
- U.S. NRC: NRC Finds No Significant Environmental Impact from Proposed Crane Clean Energy Center Restart (June 9, 2026)
- U.S. Department of Energy, Office of Energy Dominance Financing: Crane Restart project page (updated Oct. 14, 2026)
- Orrick: Microsoft Signs 20-Year PPA with Constellation (Oct. 2024)