Mochovce 4, a 471-megawatt reactor in Slovakia, began power generation on Monday, September 21, 2026, at 15:33 local time, according to World Nuclear News, which reported it the next day. The operator, Slovenske elektrarne, calls this the last major stage before commercial operation. At the time of that report the unit had not reached full power or connected to the grid.
- Q1 2029 (expected, company-reported): Duane Arnold back online
- 2027 (expected, company-reported): Crane returns 835 MW
- Oct. 13, 2026: NRC allows alternate removal of tilted Palisades fuel assembly
- Sept. 21, 2026: Mochovce 4 begins power generation
| Item | Figure | Source |
|---|---|---|
| Unit 4 capacity | 471 MW | Slovenske elektrarne |
| Share of consumption from unit 4 | About 13 percent | Slovenske elektrarne |
| Expected nuclear share after unit 4 | 77.5 percent (operator claim) | Slovenske elektrarne, WNN |
| Nuclear share of 2024 generation | About 61 percent | World Nuclear Association |
| Status | Generating power, climbing through test stages, not yet commercial | World Nuclear News |
A build that took four decades
Work on Mochovce units 3 and 4 began in 1986 and stalled in 1992. Completion work resumed around 2008 to 2009, using the original VVER-440 design with updated safety systems. The World Nuclear Association (WNA) reports that unit 3 connected to the grid on January 31, 2023, and entered commercial operation in October 2023. Slovenske elektrarne puts the cost of completing units 3 and 4 at about EUR 6.7 billion.
For unit 4, the operator and the WNA report these milestones:
- May 2026: Slovakia’s Nuclear Regulatory Authority approved commissioning (WNA).
- June 29, 2026: fuel loading began, with the regulator supervising (Slovenske elektrarne).
- Early August 2026: first criticality and minimum controlled power (World Nuclear News).
- September 21, 2026: power generation began (World Nuclear News).
Output now rises in steps of 5, 20, 35, 55, 75 and 90 percent, with checks at each level. The unit connects to the grid when it reaches 20 percent power. The final test is a 144-hour run at 100 percent power.
Where the 77.5% comes from
Slovenske elektrarne says nuclear power will reach 77.5 percent of Slovakia’s electricity consumption once unit 4 is running. It calls that the highest share of any country, ahead of France at 67 percent. The company says nuclear already covers about two-thirds of consumption and that unit 4 alone will cover about 13 percent. World Nuclear News repeated the 77.5 percent figure without naming an independent source.
The WNA’s Slovakia profile measures something different for a past year. Nuclear generated 18.2 terawatt-hours of 30.1 terawatt-hours of total generation in 2024, about 61 percent. Generation share and consumption share are different things with different baselines, so the numbers don’t directly conflict.
Who Benefits and How
- Slovak electricity users: the operator says unit 4 alone will cover about 13 percent of national consumption once it is running. That is not yet the case, since the unit is still in testing.
- Bills: no source we checked says household bills will fall, or that the unit will supply any particular number of homes.
- Everyone else: the direct effect is small. The story shows a reactor that stalled in 1992 reaching power generation, with commercial operation still ahead.
What isn’t settled
The 77.5 and 67 percent figures are the operator’s own and describe an expected share after unit 4 reaches full operation, with no independent statistic confirming them yet. The 61 percent WNA figure covers 2024 generation, so it isn’t comparable with the operator’s consumption numbers. Power generation has started, but commercial operation hasn’t. The 144-hour full-power test, regulator sign-off and any problems found along the way still lie ahead. World Nuclear News said the grid connection comes at 20 percent power, and the text we reviewed doesn’t report that it has happened.
Quick answers
Is Mochovce 4 fully operating? Not yet. It has started generating power and is climbing through test stages. Commercial operation comes after the 144-hour full-power run.
Is Slovakia really the most nuclear-dependent country? That is the operator’s claim about consumption after unit 4 runs. The figure depends on how the share is measured, and the sources we opened don’t provide an independent ranking.
What kind of reactor is it? A VVER-440 pressurized water reactor of 471 megawatts, the same type as the earlier Mochovce units, with modernized safety systems.
Who owns the plant? World Nuclear News reports that Slovenske elektrarne is majority owned by Slovak Power Holding BV, part of the Czech group EPH, with the Slovak state holding 34 percent.
Sources
- World Nuclear News: Power start-up for Mochovce 4 (Sep 22, 2026)
- Slovenske elektrarne: Mochovce 4 first fuel loading (Jun 29, 2026)
- World Nuclear Association: Nuclear Power in Slovakia (accessed Oct 13, 2026)