Google and Constellation Back 890 MW of Reactor Uprates

Google and Constellation signed a 20-year deal on Oct. 6, 2026 backing $4.3 billion of upgrades that would add 890 MW at 11 existing reactors in PJM. Here is what…

Rows of server racks in a data center room

On October 6, 2026, Google and Constellation Energy announced a 20-year power purchase agreement backing about $4.3 billion of upgrades at 11 existing nuclear units. All of them sit in the PJM grid, which covers 13 states. POWER magazine calls it one of the largest corporate-backed uprate programs announced so far.

Timeline: Reactor Restarts and New Builds

  • Q1 2029 (expected, company-reported): Duane Arnold back online
  • 2027 (expected, company-reported): Crane returns 835 MW
  • Oct. 13, 2026: NRC allows alternate removal of tilted Palisades fuel assembly
  • Sept. 21, 2026: Mochovce 4 begins power generation

See the full Reactor Restarts and New Builds timeline

The deal at a glance

Item Reported figure Source
New capacity 890 MW across 11 units in Illinois, Pennsylvania, and New Jersey Utility Dive, POWER
Investment $4.3 billion, about $4,800 per kilowatt if applied entirely to the 890 MW Canary Media
Timeline First unit by 2028; all by end of 2032 per Google POWER
Limerick 348 MW upgrade Canary Media
Salem 97 MW upgrade Canary Media
Jobs About 4,400 existing jobs sustained and about 7,200 temporary construction jobs Utility Dive

What is being upgraded

An uprate raises the licensed output of an existing reactor, usually by replacing or modifying equipment such as turbines and controls. The reactor and containment stay in place. Constellation expects the first upgraded unit online by 2028, and Google says all 890 megawatts will be online by the end of 2032, according to POWER.

Utility Dive reports that Constellation is putting up the $4.3 billion in new investment. The companies say the arrangement avoids passing costs to residential customers. A separate 15-year agreement covers 2,700 megawatts from Constellation’s existing PJM fleet, and it adds no new capacity.

Constellation has named two sites so far, according to Canary Media: Limerick, near Philadelphia, a 2,317 megawatt plant, and Salem in New Jersey, a 2,327 megawatt plant. The 11 units sit at six sites. ANS Nuclear Newswire reports the others will likely be Braidwood, Byron, LaSalle, and Quad Cities in Illinois, but Constellation has not confirmed this. POWER notes that the company has not said which of the 12 reactors at those sites is excluded, and it has not released megawatts for each site.

The NRC must review the uprates. POWER reports Constellation plans 12 uprate filings between the fourth quarter of 2026 and 2030, five extended and seven measurement uncertainty recapture uprates. PSEG, which operates Salem, plans stretch uprate applications for Salem Units 1 and 2 in the second quarter of 2027.

Why buyers want uprates

PJM expects demand to grow more than 5 percent a year over the next decade, mostly because of data centers, Canary Media reports. It also cites Reuters saying retail prices could rise as much as 60 percent by 2030. Utility Dive says PJM is about 6.8 gigawatts short of new capacity. Judi Greenwald of the Nuclear Innovation Alliance told Canary Media that uprates are among “the fastest, most practical and cost-effective ways to add reliable, clean nuclear capacity” in the near term.

Canary Media also cites Department of Energy capacity factors: nuclear 92.3 percent, combined-cycle gas 59.9 percent, wind 34.3 percent, solar 23.4 percent, and gas peakers 17.2 percent. The article does not give the year those averages cover.

Constellation CEO Joe Dominguez said the deal could “serve as a model for how technology companies and the energy industry can work together.” It follows a smaller structure announced by Georgia Power and Google and the Amazon agreement at Calvert Cliffs.

Why It Matters to You

  • If you live in the 13-state PJM region, the upgrades would add 890 megawatts to a grid that Utility Dive says is about 6.8 gigawatts short of new capacity. Capacity added to PJM can ease price pressure, but these sources give no estimate of bill effects.
  • The companies say the arrangement avoids passing costs to residential customers.
  • Timing: the first upgraded unit is expected by 2028, and Google says all 890 megawatts by the end of 2032. These are targets, and NRC reviews are still ahead.
  • Workers near the plants feel it first: about 4,400 existing jobs sustained and about 7,200 temporary construction jobs, per Utility Dive.

Where the numbers get shaky

The $4,800 per kilowatt figure is a simple division of $4.3 billion by 890 megawatts, and Utility Dive notes the investment may not cover only the uprates, so the true per-kilowatt cost is uncertain. Canary Media says the cost per kilowatt is higher than utility-scale solar with storage, a new combined-cycle gas plant, or the Three Mile Island restart, and less than half the cost of Vogtle Units 3 and 4. Only two of the 11 units have named megawatt figures, and their total, 445 megawatts, is about half of the 890. Utility Dive says approvals for this deal are not described: PJM’s “Bring Your Own New Capacity” proposal was still pending at FERC on October 7, and neither company has said whether the 890 megawatts will use it. The deal says nothing about the electric bills of any specific customer.

Quick answers

Is this a new power plant? No. It adds capacity at existing reactors through equipment upgrades. Nothing is being built from scratch.

When does the new power arrive? Constellation expects the first upgraded unit by 2028. Google says all 890 megawatts will be running by the end of 2032.

Who pays for it? Utility Dive reports Constellation is making the $4.3 billion investment, backed by Google’s 20-year purchase agreement. The companies say costs are not being passed to residential customers.

Is this the largest uprate deal ever? POWER calls it one of the largest corporate-backed uprate programs announced to date. No source calls it the largest outright.