Thirty-four thousand amps. That is the current ITER’s operators pushed through a giant superconducting magnet coil in a recent cold test, according to Fusion for Energy, the European body that supplies the coil. Full operating current is 68,000 amps, so this was a halfway mark. It was also, the agency says, the first time any ITER coil reached that level.
- 2039 (expected): ITER starts deuterium-tritium operation under its revised baseline
- 2028 (expected, company-reported): Helion targets power to Microsoft
- 2027 (expected, company-reported): CFS’s SPARC designed to reach net fusion energy
- Nov. 20, 2026: Pacific Fusion reports a New Mexico tritium licence
Fusion for Energy published its report on November 17, 2026. The test used coil number 17, one of Europe’s ten D-shaped toroidal field coils for ITER, the international fusion experiment under assembly in southern France. What is verified: the operator reported the result, and an independent outlet reported the same current and temperature. What is not shown: full-current operation, or anything about producing power.
What the Coil Test Showed
A toroidal field coil is a ring-shaped electromagnet. ITER will use 18 of them to build a magnetic cage that holds plasma, the electrically charged gas where fusion happens, away from the vessel walls. This design is called magnetic confinement, and it is how a tokamak works.
Fusion for Energy says each European coil measures 17 by 9 metres and weighs 320 tonnes. Interesting Engineering, which covered the same test earlier on November 3, 2026, gives the weight as 330 tonnes. The outlets differ on that detail. Neither changes the result.
The sequence, as the agency describes it: cool the coil to 4 kelvin (minus 269 degrees Celsius) over ten days, ramp the current to 34 kA, hold it for six hours, then discharge safely. Warming back to room temperature took another ten days. Roughly 30 experts monitored cryogenics, vacuum, power supplies and controls from the ITER control room, working in shifts.
Why Half Current Still Counts
Superconductors carry current with no electrical resistance, but only when cold enough. Getting a 300-tonne structure to 4 kelvin evenly is hard. Pushing current through it tests the joints, the insulation and the structure under enormous magnetic forces.
Interesting Engineering reports that ITER’s lead mechanical engineer Adrien Deydier called 34 kA an important step to confirm the coil “is behaving as predicted by the models.” The test also compares how the coil flexes under magnetic load against computer simulations. Matching the models is the useful part. It lowers the risk of surprises once the coils are installed.
The earlier test, of Japan’s coil number 7, reached 10 kA, according to both sources. So the trend is upward: 10 kA, then 34 kA.
| Item | Reported figure |
|---|---|
| Coil tested | European toroidal field coil 17 |
| Current reached | 34 kA (half of 68 kA operating current) |
| Temperature | 4 K (minus 269 °C) |
| Hold time at 34 kA | 6 hours |
| Earlier ITER coil test | 10 kA (Japanese coil 7) |
Source: Fusion for Energy, November 17, 2026; Interesting Engineering, November 3, 2026.
What Has Not Been Shown
The coil has not run at 68 kA. Both sources say that comes later, though their details on how differ. Fusion for Energy says Japan’s coil 19 is expected to aim for 68 kA. Interesting Engineering says spare coil 19 is scheduled for a 34 kA cooldown starting in April 2027, with a reinforcement structure added afterward to handle full current. Treat the schedule as a plan, not a promise.
These are manufacturer and operator reports. No peer reviewed paper accompanies them. One coil is also one data point. ITER needs all of its magnets to work together, including the poloidal coils and the central solenoid.
And ITER is a research machine. It is not built to put electricity on the grid. A test of one magnet says nothing about net electricity, sustained burning plasma or cost. It does say something narrower: a key hardware component behaves as designed so far.
Why It Matters to You
Fusion power is not on the grid today, and this test does not change that. Magnets are one of the hard engineering pieces. Each coil that passes testing makes the later steps less uncertain. For a reader following energy costs, the near-term effect is zero. The longer-term effect depends on whether machines like ITER, and private designs, can show these magnets work at full strength. For related engineering steps, see our look at the UK’s STEP fusion plant tender and DIII-D’s helicon current drive test.
One question worth asking at each future milestone: was the magnet tested at full current, or only part of it?
Sources
- Fusion for Energy, “Record test for European Toroidal Field coil at ITER,” November 17, 2026
- Interesting Engineering, ITER 330-tonne toroidal field coil test, November 3, 2026
- The Fusion Report, “This Week’s Fusion News,” November 20, 2026