Quick take: Fusion went from the 2006 ITER Agreement to the first laser-driven ignition at the National Ignition Facility in December 2022, and private companies now report their own milestones. No fusion plant has yet delivered electricity. The next dates are targets: Commonwealth Fusion Systems says its SPARC machine is designed to reach net fusion energy in 2027, Helion targets 2028 for power to Microsoft, and ITER’s revised baseline puts deuterium-tritium operation in 2039. Newest and upcoming dates are at the top. This page was last reviewed on November 25, 2026.
Timeline (latest first)
| When | What happened | Status | Source |
|---|---|---|---|
| 2039 | ITER’s revised baseline puts the start of deuterium-tritium operation in 2039, with full magnetic energy in 2036. The extra cost to the ITER Organization is put at 5 billion euros, still under review by members. | Expected | ITER, our ITER magnet report |
| 2028 | Helion says its Orion plant in Malaga, Washington will supply power to Microsoft by 2028. Helion says construction began in July 2025. | Expected (company-reported) | Helion release |
| April 23, 2027 | Planned contract start for UK STEP prototype plant systems. The UK Fusion Energy tender (about 115 million pounds before VAT, five lots) has bids due January 29, 2027 and an award decision on April 6, 2027. The notice reserves the right to make no award. | Expected | Our STEP tender report (we did not open the primary notice) |
| 2027 | Commonwealth Fusion Systems says SPARC is designed to reach net fusion energy (Q greater than 1) in 2027, and that its first ARC plant in Chesterfield County, Virginia is planned to start generating power in the early 2030s. Google signed a 200 MW offtake agreement. | Expected (company-reported) | CFS blog, June 30, 2025 |
| November 20, 2026 | Pacific Fusion says New Mexico regulators approved a licence for it to possess and use tritium at its Albuquerque campus. The company calls it the first such licence the state has issued to a private fusion company. We found no independent confirmation. | Done (company-reported) | Our report (we did not open the company release) |
| February 13, 2026 | Helion says its Polaris machine is the first privately developed fusion machine to show measurable deuterium-tritium fusion. It reports D-T fuel use began in January 2026 and plasma reached 150 million degrees C. No electricity from fusion has been reported. | Done (company-reported) | Helion newsroom |
| April 7, 2025 | The National Ignition Facility records a record yield of 8.6 MJ from 2.08 MJ of laser energy, a target gain of 4.13. | Done | Lawrence Livermore |
| February 12, 2025 | CEA-IRFM sustains a hydrogen plasma in the WEST tokamak in France for 1,337 seconds, about 22 minutes. | Done | CEA-IRFM |
| January 20, 2025 | China’s EAST tokamak holds a steady-state high-confinement plasma for 1,066 seconds, replacing its earlier 403-second record from 2023. | Done | Chinese Academy of Sciences |
| February 8, 2024 | UKAEA reports a JET record of 69 megajoules from 0.2 milligrams of fuel in its final experiments. JET ended scientific operations at the end of December 2023. | Done | UK government |
| May 2023 | DOE selects eight companies for its Milestone-Based Fusion Development Program, with $46 million for an initial 18 months. | Done | ANS |
| December 5, 2022 | The National Ignition Facility achieves fusion ignition, with 3.15 MJ of fusion output from 2.05 MJ delivered to the target. | Done | DOE |
| November 21, 2006 | Ministers sign the ITER Agreement in Paris. The seven parties are China, the EU, India, Japan, Korea, Russia and the US. | Done | ITER |
What the timeline tells you
Records so far measure physics, not power. NIF’s ignition and later higher yields count fusion energy released against laser energy on the target, not against the electricity needed to run the facility, and the WEST, EAST and JET records measure duration or energy in test machines. The dates ahead are mostly company targets, and ITER’s own schedule has already been pushed to 2039. Treat every 2027 and 2028 date as a goal.
Related reading
- Helical Fusion Reports Up to 19.2 Billion Yen for Stellarator Demo
- Pacific Fusion Reports New Mexico Licence to Use Tritium
- UK Opens £115M Tender for STEP Fusion Plant Systems
- ITER Reports a Europe-Built Magnet Reached 34,000 Amps in Cold Test
- DIII-D Reports Helicon Current Drive Result in a Tokamak
Dates marked “expected” or “scheduled” are plans, not results. This page will be reviewed quarterly.