Home » Advanced Nuclear Fuel Timeline: From 2020 to 2036

Advanced Nuclear Fuel Timeline: From 2020 to 2036

Quick take: Advanced reactors need fuel that barely exists at scale: high-assay low-enriched uranium (HALEU), TRISO fuel and new enrichment capacity. In the past three years the US produced its first HALEU at Piketon (2023), banned Russian uranium imports (2024), licensed the first TRISO fuel plant (February 2026) and awarded $2.7 billion for enrichment (January 2026). Most new enrichment capacity is still years away, with Centrus targeting 2029 and Urenco’s new cascades starting in 2032. Newest and upcoming dates are at the top. This page was last reviewed on November 25, 2026.

Timeline (latest first)

WhenWhat happenedStatusSource
2032 (first new cascades); 2036 (remaining cascades)Urenco’s 2.1 million SWU, 24-cascade expansion at Eunice, New Mexico is under way. World Nuclear News lists 2032 for the first new cascades producing and 2036 for the remaining cascades installed. A separate 700,000 SWU addition is due in 2027.ScheduledWorld Nuclear News, our fuel supply report
2029Centrus expects its first new enrichment capacity at Piketon, Ohio, to come online. Centrus reports it shipped its first Oak Ridge-built centrifuge to Ohio. The DOE task order is $900 million, up to $1.07 billion with HALEU options.Expected (company-reported)World Nuclear News, our report
By January 1, 2028DOE can waive the Russian low-enriched uranium import ban only until January 1, 2028. The ban took effect August 11, 2024.ScheduledWorld Nuclear News
Early 2027Global Laser Enrichment (GLE) says it expects an NRC licence for its planned Paducah, Kentucky laser enrichment plant in early 2027. GLE filed its full application in July 2025. Cameco has agreed to buy all future output. A final investment decision is still pending.Expected (company-reported)World Nuclear News, our report
September 9, 2026Centrus and Radiant sign a definitive multi-year HALEU supply contract for Kaleidos microreactors. Deliveries start “before the end of the decade.” Volumes and price were not disclosed.DoneWorld Nuclear News, our report
June 2026BWXT reports that its TRISO fuel supported the first criticality of Antares Nuclear’s reactor at Idaho National Laboratory. BWXT also processed the HALEU feedstock.Done (company-reported)BWXT release
February 13, 2026The NRC licenses TRISO-X, an X-energy subsidiary, to make TRISO fuel at Oak Ridge, Tennessee. The NRC calls it the first US approval of a category II fuel fabrication facility.DoneNRC release 26-019, our report
January 2026DOE awards $2.7 billion for enrichment. American Centrifuge Operating (Centrus), General Matter and Orano each get $900 million, and GLE gets about $28 million subject to final contract negotiations.DoneANS
November 2025X-energy and TRISO-X announce that aboveground construction has started on the TX-1 fuel facility in Oak Ridge. The exact start date is not stated.Done (company-reported)ANS, our report
April 9, 2025DOE conditionally allocates its first HALEU to five developers: TRISO-X, Kairos Power, Radiant, Westinghouse and TerraPower.DoneDOE
May 2024The Prohibiting Russian Uranium Imports Act is signed. DOE waivers are capped by annual limits and end on or before January 1, 2028.DoneDOE
November 2023Centrus produces the first 20 kg of HALEU at Piketon, Ohio. DOE says it is the first such US production in more than 70 years.DoneDOE, World Nuclear News
2022DOE announces a cost-shared award of about $150 million to Centrus’s American Centrifuge Operating to run a 16-centrifuge HALEU cascade at Piketon. The year comes from our earlier report and World Nuclear News; the DOE page is undated.DoneDOE, our report
2020The Energy Act of 2020 directs DOE to set up the HALEU Availability Program. DOE’s page gives only the year.DoneDOE

What the timeline tells you

Licensing and funding have moved faster than fuel production. The US has a licensed TRISO plant and $2.7 billion in enrichment awards, but the new capacity those awards pay for is dated 2029 and later. Meanwhile the waiver window for Russian uranium closes at the start of 2028. Several dates here are company targets rather than regulator decisions, so watch the NRC’s GLE licensing decision expected in early 2027 and Centrus’s progress toward 2029.

Related reading

Dates marked “expected” or “scheduled” are plans, not results. This page will be reviewed quarterly.