TRISO-X has completed the 214,000 square foot building for its TX-1 fuel plant in Oak Ridge, Tennessee. Equipment installation comes next, and no start date has been given.

Interior of a large industrial factory hall with heavy machinery, illustrating a fuel fabrication plant build-out

TRISO-X, the fuel-making subsidiary of reactor developer X-energy, has completed the building for its TX-1 fuel fabrication plant in Oak Ridge, Tennessee. World Nuclear News reported the milestone on September 25, 2026. X-energy’s own release, dated August 24, 2026, announced the move to the next construction phase. TX-1 is not a reactor. It is a plant meant to make TRISO fuel pebbles for X-energy’s Xe-100 reactor.

Timeline: Advanced Nuclear Fuel

  • 2029 (expected, company-reported): Centrus’s first new enrichment capacity at Piketon
  • Early 2027 (expected): GLE’s NRC licence for its Paducah laser plant
  • Sept. 9, 2026: Centrus and Radiant sign a HALEU supply contract
  • Feb. 13, 2026: NRC licenses the TRISO-X fuel plant

See the full Advanced Nuclear Fuel timeline

Finished versus still ahead

Item Done Still ahead
Building 214,000 square foot process equipment and administration building complete Auxiliary buildings, interior build-out, fabrication equipment installation, graphite matrix powder building
Licence NRC 40-year Special Nuclear Material License, granted earlier in 2026 TX-2, the planned larger plant, is covered by the same license but not built
Output None yet Planned 700,000 pebbles a year, 5 MTU (X-energy)
State support $11 million Tennessee grant, July 2026 (World Nuclear News) Not applicable
Start of operations No date given Neither source says when

What the shell is for

Clark Construction Group remains the general contractor. TRISO-X says the plant will make about 700,000 TRISO pebbles a year, equal to 5 metric tons of uranium, enough to fuel up to 11 Xe-100 reactors. TRISO fuel packs uranium kernels inside layers of carbon and ceramic. The Nuclear Regulatory Commission granted TRISO-X its license earlier in 2026, and X-energy calls it the first NRC Category 2 license for processing high-assay low-enriched uranium (HALEU) fuel. The license covers TX-1 and the planned larger TX-2.

TRISO-X president Joel Duling said: “Every milestone brings us closer to establishing a new domestic source of advanced nuclear fuel.” He also called TX-1 “the first new commercial nuclear fuel facility this country has built in more than half a century.” That is the company’s description, and we did not verify it independently.

Who the fuel is for

X-energy says TX-1 supports its first proposed Xe-100 deployment with Dow at the UCC Seadrift Operations site on the Texas Gulf Coast. That project is a proposed four-unit plant meant to supply power and industrial steam. X-energy is also advancing the Cascade Advanced Energy Facility with Energy Northwest in collaboration with Amazon. Neither project has been built.

Fuel supply matters because advanced reactor developers have relied on a thin domestic HALEU supply chain. See our look at the state of nuclear fuel supply. TX-1 makes pebbles from enriched uranium and doesn’t enrich uranium itself, so it still depends on enrichers such as Centrus for HALEU.

Who Benefits and How

This is supply-chain news, and the benefit is indirect. If TX-1 starts up, advanced reactor developers such as X-energy, and the customers behind proposed projects with Dow and Amazon, would have a domestic fuel source for the Xe-100. Ordinary electricity users won’t see anything soon: the plant isn’t operating, no start date is public, and the reactors it would feed haven’t been built.

Where it falls short

Neither source gives a date for when TX-1 will start making fuel. The sources we opened give no job figures. The 700,000 pebble output and the 11-reactor figure are planned capacity from X-energy, not production. Dow and Amazon are named as customers or collaborators on proposed projects, and the sources don’t say those reactors have started construction.

Four quick questions

Is TX-1 operating?

No. The building is finished. Equipment installation and other construction phases remain, and no start date is public.

What is TRISO fuel?

TRISO stands for tri-structural isotropic. Each particle holds a uranium kernel inside layers of carbon and ceramic, and the particles are packed into graphite pebbles.

Does TX-1 enrich uranium?

No. It fabricates fuel from HALEU. Enrichment happens at other facilities.

What comes after TX-1?

World Nuclear News says TX-2 is planned as a larger second facility, and TX-L as a fuel lab.