Cameco signed an exclusive offtake deal for everything Global Laser Enrichment’s planned Paducah plant will make. The plant still needs an NRC license and a final investment decision.

Abstract blue laser light technology, symbolizing laser enrichment technology for nuclear fuel

On September 16, 2026, World Nuclear News reported that Cameco agreed to buy all future production from the Paducah Laser Enrichment Facility (PLEF), a planned plant in western Kentucky. Global Laser Enrichment (GLE) would build and run it. GLE is owned 51% by Australia’s Silex Systems and 49% by Cameco, and Silex is the exclusive licensee of the SILEX laser technology through GLE. The plant has not been built, and it does not yet have its NRC license.

Timeline: Advanced Nuclear Fuel

  • 2029 (expected, company-reported): Centrus’s first new enrichment capacity at Piketon
  • Early 2027 (expected): GLE’s NRC licence for its Paducah laser plant
  • Sept. 9, 2026: Centrus and Radiant sign a HALEU supply contract
  • Feb. 13, 2026: NRC licenses the TRISO-X fuel plant

See the full Advanced Nuclear Fuel timeline

Who Benefits and How

Not utility customers, at least not visibly. Nothing here shows a lower power bill, and enrichment is only one part of fuel cost. The nearer benefit is local: the state announced 240 jobs in McCracken County, though those are commitments tied to a 15-year incentive term and not yet employment. Reactor owners could eventually gain another fuel source, but only if the plant gets its license, a final investment decision and a working commercial process.

The deal and the technology

The agreement is an exclusive offtake. Cameco buys natural uranium hexafluoride and enriched uranium products from PLEF, and GLE’s price follows Cameco’s average realised price, net of selling costs, calculated annually across Cameco’s long-term contract portfolio. GLE avoids building its own sales team. Silex says the deal supports a future final investment decision (FID), which means the company has not yet committed to build.

The plant would use SILEX laser technology instead of the centrifuges that supply essentially all commercial enrichment today. GLE reached Technology Readiness Level 6 in 2025 after a large-scale demonstration at its Test Loop facility in Wilmington, North Carolina, according to World Nuclear News. TRL 6 means a prototype has been shown in a relevant environment, not that the technology runs commercially.

PLEF would sit on a 665-acre site next to the former Paducah Gaseous Diffusion Plant. Under a 2016 Department of Energy contract, GLE plans to re-enrich high-assay depleted uranium tails left from past enrichment, expecting about 70,000 tonnes of new feed from “200,000-plus tonnes” of tails over the plant’s life. Those tails are a stockpile that becomes useful only if re-enrichment proves economic. GLE says it will serve markets for low-enriched uranium, LEU+ (5% to 10% uranium-235), and high-assay LEU.

Item Reported figure Source
Planned investment $1.76 billion Kentucky Cabinet for Economic Development (Mar 26, 2026)
New jobs 240, McCracken County, average $62 an hour including benefits Kentucky Cabinet for Economic Development
State incentives Up to $24 million plus up to $3 million (preliminary) Kentucky Cabinet for Economic Development
Tails to re-enrich 200,000-plus tonnes, about 70,000 tonnes of new feed World Nuclear News (Sep 16, 2026)
NRC license Application completed July 2025, licence expected early 2027 (GLE CEO) World Nuclear News

What is still unsettled

The plant is under NRC license review, and the early 2027 date is GLE’s CEO expecting a licence, not a decision. Silex says the offtake supports a final investment decision, but the sources we opened don’t announce one. The $1.76 billion and 240 jobs are GLE’s commitments as announced by the state. No source we opened gives PLEF’s planned enrichment capacity, so we can’t say how much US demand it would meet. The tails figure also varies: World Nuclear News and Kentucky cite more than 200,000 tonnes, while the International Panel on Fissile Materials says DOE sold GLE about 300,000 tonnes of depleted uranium in 2016. Another firm, General Matter, has also leased land at the site for similar work. For context, nuclear supplied about 19% of US electricity in 2023, according to EIA.

Quick answers

What are depleted uranium tails?

They are the material left after earlier enrichment removed most of the uranium-235. Some tails still hold enough uranium-235 to re-enrich, which is what GLE plans to do at Paducah.

Does laser enrichment replace centrifuges?

Not now. GLE has demonstrated its laser process at test scale and has not yet run a commercial plant.