- Six Flags Magic Mountain in Valencia, California, says a 12.37-megawatt solar carport is online, announced October 1, 2026.
- Solar Builder and Electrek describe it as the largest solar carport in California.
- A 2-megawatt, 8-megawatt-hour battery and 109 EV charging connectors are part of the project.
- Generation, emissions and water figures are company and installer estimates, not measured results.
What was built
The park broke ground on November 1, 2023. Solar Optimum of Glendale, California built the project, with DSD Renewables as a partner. Electrek reports 22,908 bifacial panels on about 637,000 square feet of canopy, spread over 36 carport structures. Bifacial panels collect light on both sides. The canopies cover about 4,315 parking spaces, 3,544 for guests and 771 for employees.
A 2-megawatt, 8-megawatt-hour battery sits on site, about four hours of output at full power. The site also has 109 EV charging connectors across guest and employee lots, according to Electrek, which doesn’t report pricing or charger speeds. The system stays connected to the Southern California Edison grid and is not an isolated microgrid. Solar Builder says extra energy can be exported or used during high-demand periods.
It isn’t the park’s first solar. Electrek notes earlier systems at Six Flags Discovery Kingdom in Northern California and Six Flags Great Adventure in New Jersey. As for size, the sources call this California’s largest carport. Six Flags says it is one of the largest single-site commercial carport projects in the US.
What the company says it will deliver
The company and its installer expect about 20.8 million kWh a year (Electrek, Solar Optimum), which Solar Builder and Solar Optimum put at the equivalent of 2,874 homes a year. Solar Builder adds more than 8,000 tons of CO2 avoided and more than 10 million gallons of water conserved each year. The stated goal is to offset 100% of annual electricity use at Magic Mountain and Hurricane Harbor Los Angeles.
Park president Brian Oerding called the energization “a transformative moment for Six Flags Magic Mountain and our sustainability journey.”
Why It Matters to You
If you visit the park, you get shaded parking, which the company says is an aim, and 109 EV charging connectors, though pricing and speeds aren’t reported. The system feeds the park’s electrical system rather than customers directly, so there is no bill credit or direct payoff for visitors. It is energized now, but its output has not yet been measured.
What the numbers don’t show
- All generation, emissions and water figures are project estimates from the company and its installer. The system has only just started operating, so no measured output exists yet.
- The sources don’t explain how the CO2 and water figures were calculated. Water savings usually reflect water that power plants would otherwise use, but the reports don’t say.
- “Offset 100%” is an annual accounting goal. The park stays on the grid and draws power when the sun is down.
- No source gives the project’s cost, the park’s electric bill, or expected dollar savings.
- The “2,874 homes” comparison converts annual kilowatt-hours into average household use. The sources don’t state the household figure used.
- No source measured temperatures at this lot, so the cooling benefit of the shade is unconfirmed.
Frequently asked questions
Does the carport power the rides?
It feeds the park’s electrical system, which stays connected to Southern California Edison. The company expects annual generation to roughly match use at the two parks.
Can visitors charge electric cars?
The project adds 109 EV charging connectors across guest and employee lots, according to Electrek. Pricing and charger speeds are not reported.
Is it the biggest solar carport in the country?
Not by the sources’ claim. They call it California’s largest. Six Flags says it is one of the largest single-site commercial carport projects in the US.
Sources
- Electrek: Six Flags has installed one of the largest solar carports in the US (Oct 5, 2026)