An electric vehicle battery doesn’t die when it stops being good enough for the road. It just gets a less demanding job. That’s the idea behind Bexar Martinez, a battery site B2U Storage Solutions has brought into commercial operation in CPS Energy territory near San Antonio, Texas. The company says it is built entirely from repurposed EV batteries. It is B2U’s second second-life project in Texas, and it sells into the ERCOT market.
Utility Dive reported on September 15, 2026, that B2U announced commercial operations the week before, in a press release dated September 9. The site stores 28 megawatt-hours and is rated at about 10 megawatts. It uses more than 700 former EV battery packs.
Second-life batteries are packs that no longer suit daily driving, because their range has dropped, but that still hold useful charge. A stationary site can charge them when power is cheap or solar output is high and discharge when demand peaks. How much that helps San Antonio depends on how the site is dispatched, and no results for this plant have been published by ERCOT or CPS Energy.
The cost claim, and who is saying it
B2U says its installed costs can be as much as 40% lower than competing battery storage systems “with equivalent reliability and performance.”
That is a company claim, not an independent comparison, and it says “as much as,” not “typically.” The projects also qualify for the domestic content bonus under the Section 48(e) investment tax credit, per Utility Dive.
Supply is the other half of the story. B2U signed an agreement in June 2026 to repurpose batteries from Waymo vehicles as they leave that fleet, and the company expects supply to reach hundreds of megawatts of storage over time. That is an expectation, not delivered capacity, and deliveries depend on when those vehicles age out. For scale, B2U says it has at least 100 MWh of second-life capacity operating and plans over 50 MWh more in ERCOT within six months.
Why It Matters to You
If you’re a CPS Energy customer, don’t expect a lower bill from this plant. Wholesale storage costs affect rates only indirectly, and the coverage doesn’t say CPS Energy buys the output or passes savings to customers. The nearer-term payoff is for the battery industry: if the cost claim holds, used EV packs could become a cheaper source of grid storage as more vehicles retire.
What’s still unproven
- The 40% cost advantage is B2U’s own claim. No independent study backs it in the coverage reviewed.
- Both Texas sites run on a merchant basis for now, meaning they earn market prices while B2U negotiates tolling agreements with third parties. Revenue isn’t locked in.
- Nothing found says this plant lowers anyone’s electric bill, and there’s no figure for homes served. Energy in MWh and homes are different measures, so we don’t convert.
- No operating record exists yet, so reliability claims are untested.
Quick answers
What is a second-life EV battery?
It is a battery pack removed from a vehicle after its range drops, then reused in less demanding stationary storage.
Who owns the site, and does it lower my CPS Energy bill?
B2U Storage Solutions built and operates it, selling into the ERCOT market. A lower bill isn’t promised: the coverage doesn’t say CPS Energy buys the plant’s output or passes savings to customers.
Sources
- Utility Dive: Second-life battery project is B2U’s second in ERCOT, with more on the way (Sep 15, 2026)