Home » Nuclear Fission » Haiyang 3 Completes Hot Tests Ahead of 2026 Fuel Load Target

Haiyang 3 Completes Hot Tests Ahead of 2026 Fuel Load Target

Haiyang 3, a CAP1000 unit in Shandong, finished hot functional tests on August 13, 2026. The operator aims to load fuel and connect to the grid within the year.

Coastal landscape with wind turbines, representing the Haiyang 3 nuclear reactor's coastal China location

Haiyang unit 3, a CAP1000 reactor on China’s Shandong coast, has finished hot functional testing. World Nuclear News reported on August 17, 2026 that the hot tests ended on August 13. The plant’s operator, State Power Investment Corporation (SPIC), says it aims to load fuel and connect the unit to the grid within 2026.

What’s new

  • Hot functional testing finished on August 13, 2026.
  • 53 commissioning test procedures covering 308 test chapters were completed, per World Nuclear News.
  • Transient tests, including a non-nuclear steam turbine start-up and a main pump coast-down, passed on the first attempt.

What stays the same or isn’t confirmed

  • The unit has no fuel and is not producing electricity.
  • Regulators must still approve fuel loading separately.
  • The fuel load and grid dates are SPIC’s goals, not commitments. Nuclear start-up schedules often slip.
  • The test counts come from the project announcement as relayed by World Nuclear News. We found no independent audit of them.

What the test involved

In a hot functional test, engineers run the plant at operating temperature and pressure without nuclear fuel. Heat comes from the reactor coolant pumps rather than from fission. The goal is to check that pumps, valves, piping and control systems behave as designed before fuel arrives. World Nuclear News also cites 11 temperature rise and fall test platforms and 30 periodic tests. CNNC Fifth Construction Company, a subsidiary of China National Nuclear Corporation, carried out the hot tests.

The CAP1000 is China’s version of the Westinghouse AP1000. It uses passive safety features, such as gravity-driven water and natural circulation, that aim to cool the core without pumps in some accident sequences. Hot testing checks the conventional plant systems around those features. It does not prove how the passive systems would perform in an accident, which is a job for separate analyses, component tests and regulatory review. Passing the first-attempt transient tests is a good sign for the build, but it is not a license to load fuel.

Schedule and site

Item Reported detail Source
Hot tests finished August 13, 2026 World Nuclear News
Fuel load and grid connection SPIC aims for “within the year” (2026) World Nuclear News
Units 3 and 4 fully operational Scheduled for 2027 World Nuclear News
Site plan Six 1,000 MW reactors planned; about 40 billion kWh a year once four units operate World Nuclear News

The 40 billion kWh a year figure applies when four units operate. The source does not say how many units operate today, and units 3 and 4 are still being commissioned. No source we found supports a dollar figure for downtime costs, so we give none.

Why It Matters to You

  • No one is getting power from Haiyang 3 yet. The unit has no fuel.
  • If SPIC meets its goal, the unit would load fuel and connect to the grid within 2026, and units 3 and 4 are scheduled to be fully operational in 2027.
  • Electricity customers in the region served by the site would be the first to feel any effect, once the plant is running. The sources do not mention bills or prices.

Quick answers

Is Haiyang 3 producing electricity? Not yet. Hot tests run without fuel. SPIC aims to load fuel and connect to the grid within 2026.

What is a CAP1000? It is the Chinese version of the Westinghouse AP1000, a pressurized water reactor with passive safety features.

Why test without fuel? Operators can find leaks, control problems and equipment faults at full temperature and pressure before radioactive fuel is in the core.

What comes after hot testing? Regulatory approval, fuel loading, first criticality, power ascension and grid connection. Commercial operation follows after further testing.