Eighty-two percent. That is roughly how much of Cerritos College’s yearly electricity use a new solar canopy in Norwalk, California is now projected to cover, according to the college and its solar developer, ForeFront Power.
On Nov. 16, Cerritos College and ForeFront Power marked the completion of a 6.5-megawatt solar canopy built over two campus parking lots. ForeFront Power financed, built and now operates the system under a long-term contract with the college. The company says it is the largest single-campus solar canopy at any community college in the country, a claim about community colleges specifically, not about solar carports in general. Cerritos College serves roughly 21,000 students a year across southeastern Los Angeles County, in communities that include Artesia, Bellflower, Downey, Hawaiian Gardens, La Mirada and Norwalk itself.
From Parking Spaces to a Power Plant
The canopy sits above Parking Lot 1 and Parking Lot 10, turning two stretches of blacktop into shaded, solar-covered structures. Cerritos College did not pay to build it and did not use bond money either. Instead, the college signed a power purchase agreement, or PPA, with ForeFront Power. Under that kind of deal, the developer covers design and construction costs, keeps ownership of the equipment, and sells the college electricity at a fixed rate meant to stay below what the local utility would otherwise charge. It is the same no-upfront-cost structure behind a recent Massachusetts nonprofit school’s solar array, just scaled up to a 6.5-megawatt system.
The project took years to reach this point. Cerritos College’s Board of Trustees approved the plan in 2022 after a competitive solicitation that drew seven proposals from more than 30 vendors. Construction on the two parking lots began near the end of 2024, and this month’s completion closes out a process that started with contracts signed two years earlier. Projects built this way often shift in scale and timeline as engineering, permitting and utility interconnection work plays out, which is part of why the numbers below moved between the early estimate and the finished system.
What Changed Between the Estimate and the Finished Project
Cerritos College and ForeFront Power gave different numbers for this project at different stages. Here is how the public estimates compare with what the two organizations are saying now that construction is done.
| Metric | 2025 Public Estimate | At Completion (Nov. 2026) |
|---|---|---|
| System size | 6.5 MW-DC | 6.5 MW-DC |
| Projected annual electricity offset | 85% of campus use | 82% of campus use |
| Projected savings over the contract term | $16 million | More than $25 million |
Source: Cerritos College public statements from 2025 and the Nov. 16, 2026 completion announcement from Cerritos College and ForeFront Power.
The offset estimate dropped three points while the savings figure rose by more than $9 million. Neither organization explained the shift in the materials reviewed for this story, and both numbers come from the companies themselves rather than an independent audit. Moving from design-stage projections to as-built performance estimates is routine on long-term energy contracts, since electricity rates, interconnection terms and construction specifics can all shift between a signed deal and a finished system.
Independent trade coverage adds detail the announcement itself does not include. Solar Builder magazine reports the canopy is expected to generate more than 10.8 gigawatt-hours of electricity a year, enough to cover the annual use of nearly 1,900 homes in the surrounding area, and that it is projected to avoid about 5,475 metric tons of carbon dioxide annually, similar to removing more than 1,270 gas-powered cars from the road for a year.
What the Announcement Leaves Out
- Neither ForeFront Power nor Cerritos College has disclosed what the project cost to build.
- Neither has named the solar panel manufacturer or said whether the panels were made in the United States.
- It is not clear whether the canopy includes electric vehicle charging, something ForeFront Power has added at other California campuses it has built for.
- The “largest” claim comes from ForeFront Power itself and applies specifically to community colleges. California’s largest solar carport overall is a separate, larger project: the 12.37-megawatt system a competing developer energized at Six Flags Magic Mountain, which is nearly twice the size but sits at a theme park, not a school.
Why It Matters to You
For the roughly 21,000 students who take classes at Cerritos College each year, this is not really about parking lot shade, welcome as that is on hot Southern California afternoons. It is about the college’s operating budget. “Every dollar we save on energy is a dollar we can reinvest in our students,” said Felipe Lopez, the college’s executive vice president of business services, in the completion announcement.
That reinvestment tends to land in the programs that run on discretionary funding: tutoring centers, lab equipment, student support services and the workforce training the college runs for the surrounding region. A public college spending less on electricity has more room to spend elsewhere, even if the exact dollar amounts take years to show up in a line item. Other public institutions are making a similar bet. Minnesota’s Solar for Schools program has now helped nearly 400 K-12 campuses cut energy bills the same way, through the same basic no-upfront-cost structure.
There is a neighborhood angle too. Cerritos College sits in a stretch of Los Angeles County that includes Artesia, Bellflower, Downey, Hawaiian Gardens, La Mirada, Norwalk and parts of several nearby cities. Cutting more than 5,000 metric tons of carbon emissions a year, if the projections hold, means less fossil fuel generation serving that part of the county. Those emissions and savings figures are projections based on current electricity rates and expected sunlight, not guarantees, but they are the same kind of projection utilities and school districts routinely rely on when signing long-term power contracts like this one.
Sources
- Business Wire: Cerritos College and ForeFront Power Complete Largest Community College Solar Canopy in the U.S. (Nov. 16, 2026)
- Solar Builder magazine: Projects Weekly roundup (Nov. 23, 2026)
- Cerritos College: Cerritos Blue is Going Green (May 6, 2025)
- Cerritos College: State of the College address (May 2, 2025)