Preston Park Elementary School in Roanoke, Virginia opened the doors of its brand-new building this past September. Two months later, the school is getting a second major addition: a rooftop covered in solar panels.
Secure Solar Futures, a Staunton, Virginia-based solar developer, announced on November 11 that it will install a 313-kilowatt solar power system at the school, located at 3142 Preston Avenue NW. The 531 bifacial panels, made by VSUN Solar in Houston, are expected to cover 67% of the elementary school’s annual electricity use once the system is running, according to the company’s announcement, confirmed by Solar Power World’s independent coverage of the project.
- What’s happening: A 313-kW rooftop solar array is coming to Preston Park Elementary, built and owned by Secure Solar Futures and financed mainly by Pardee Renewable Energy LLC.
- Cost to the school: Nothing upfront. Roanoke City Public Schools buys the power under a 25-year agreement at a rate the developer says will stay below the local utility’s.
- Projected payoff: $581,000 in avoided electricity costs over the agreement’s term, plus an estimated 371 metric tons of avoided carbon pollution every year.
- Timeline: Construction is expected to start later this year. No completion date has been announced.
Inside the Preston Park Solar Agreement
The arrangement is a power purchase agreement, or PPA, a financing structure that has become common for cash-strapped school districts. Secure Solar Futures designs, builds and owns the equipment. Pardee Renewable Energy LLC, a subsidiary of Pardee Resources Company, supplies most of the money. Roanoke Schools pays nothing to get the panels installed and instead buys the electricity they generate, at a rate the companies say will run below what the local utility charges for the full 25-year term.
In its first year, the system is projected to produce 421 megawatt-hours of electricity, enough to supply roughly 44 average Virginia homes for a year, though all of it will go to running the school rather than the grid at large. Once the 25-year agreement ends, the district gets the option to buy the equipment outright for a nominal price and keep using it for whatever is left of a solar panel’s typical 35- to 40-year working life.
One School in a 29-Site Build-Out
Preston Park is the latest addition to a solar program Roanoke City Public Schools has been building since school-plants director Jeff Shawver opened negotiations with utility Appalachian Power back in 2018. The first deal, a 1.7-megawatt agreement covering seven buildings, was approved in early 2024. Reporting from Canary Media, the nonprofit clean energy outlet, found the program has since grown to nearly 9.4 megawatts installed or planned across 29 sites, enough to cover about 44% of the district’s electricity needs and cut its power bills by more than $22 million over 35 years. Many of the installations come bundled with new roofs, which Canary Media reports could save the district another $24 million it would otherwise spend on roof replacements.
Shawver told Canary Media the roof work is as big a win for his team as the solar itself: “That’s a happy day for that person,” he said of the warranties that come with the bundled work. Roanoke’s two high schools, which double as official disaster shelters, got a solar-and-battery microgrid earlier this year so they can keep running during power outages, a project covered here when it was announced. Virginia’s public schools now rank eighth nationally for solar capacity, and Roanoke accounts for a large share of that total on its own, according to nationwide data on school solar adoption.
What’s Still Unclear
- Secure Solar Futures hasn’t said what the Preston Park system will cost to build, since the company and its financing partner, not the school district, are paying for it.
- The 67% offset and $581,000 savings figures are projections, not guarantees. They depend on the school’s electricity use staying roughly where it is now. Preston Park just absorbed about 124 additional students in a districtwide boundary realignment this fall, which could push its energy use higher than planned.
- District-wide savings estimates vary by source and by date, likely because the solar program keeps growing. Canary Media’s September count of $22 million in energy savings plus $24 million in avoided roof costs doesn’t match an RCPS announcement from last year that cited $46.5 million for a smaller, 17-site version of the same program. Neither source published the full math behind its number.
Why It Matters to You
- If you pay taxes or have kids in Roanoke schools: the project costs the district nothing upfront, and every dollar it isn’t spending on electricity is a dollar that can go toward classrooms instead.
- If you live near the school: less demand on gas and coal-fired power plants means a small, shared reduction in regional air pollution, not a guarantee of cleaner air on any one block.
- If you’re skeptical of the payoff: none of this is money in hand yet. It’s a 25-year bet that a private developer keeps the panels running as promised, and that electricity prices don’t fall enough to erase the advantage.
Preston Park is one school in a 29-site build-out that is still filling in. Whether Roanoke hits that full 9.4-megawatt target, and whether the savings numbers hold up once more of the program is actually built, is something only a few more years of school budgets will show.
Sources
- Secure Solar Futures, via GlobeNewswire: Roanoke City Schools to Add 313 kW Solar Power System (Nov. 11, 2026)
- Solar Power World: Secure Solar Futures set to install 313-kW array on Virginia elementary school (Nov. 12, 2026)
- Canary Media: A Virginia school district pioneers solar and battery microgrids (Sept. 8, 2026)
- Cardinal News: Roanoke School Board approves changes to attendance zones for 2026-2027 (May 28, 2026)