What do you do with a half-built plutonium plant that the federal government walked away from, not once but twice? If you’re Newcleo, you try a third approach, with new partners and a different fuel source.
- 2029 (expected, company-reported): Centrus’s first new enrichment capacity at Piketon
- Early 2027 (expected): GLE’s NRC licence for its Paducah laser plant
- Sept. 9, 2026: Centrus and Radiant sign a HALEU supply contract
- Feb. 13, 2026: NRC licenses the TRISO-X fuel plant
The French reactor developer announced on November 16 that it’s partnering with Washington, D.C.-based Curio on recycled nuclear fuel. Curio will use its NuCycle technology to pull plutonium, uranium and other materials out of used reactor fuel. Newcleo wants to turn that material into fuel at a planned Savannah River MOX fuel plant near Aiken, South Carolina. Nuclear Newswire and World Nuclear News both reported on the agreement this week.
Nothing has broken ground. Newcleo hasn’t even filed an actual license application for the facility yet. But the deal adds a real recycling partner, already running lab tests inside national labs, to a site with an expensive and unfinished history.
A Site With a Troubled History
This isn’t the first attempt at making MOX fuel at Savannah River. In 2005, the Nuclear Regulatory Commission approved a construction license for the Mixed Oxide Fuel Fabrication Facility, known as the MFFF, at the same site. The project grew out of a 2000 agreement between the US and Russia, in which each country promised to dispose of 34 metric tons of surplus weapons-grade plutonium by turning it into reactor fuel.
Construction started in 2007. Costs and delays kept piling up. The Obama administration asked to end the project’s funding, and the first Trump administration chose a cheaper disposal method instead, called dilute and dispose. The Department of Energy told its contractor to stop construction in October 2018. The NRC pulled the facility’s construction authorization in February 2019. No fuel assembly was ever produced.
The site didn’t stay empty, though. In 2022, the DOE hired a new contractor to convert the half-finished MFFF building into something else entirely: the Savannah River Plutonium Processing Facility, which will make plutonium pits for the National Nuclear Security Administration’s weapons stockpile. Full construction authorization for that project came through on October 15 this year. Separately, the DOE said in March 2026 that it will restart a 1980s-era building at the site called HB Line, originally built to make plutonium-238 for space missions, to eventually help produce MOX fuel for advanced reactors.
Inside the Savannah River MOX Fuel Deal
Curio’s NuCycle process pulls plutonium, uranium and other reusable material out of spent nuclear fuel that currently just sits in storage as high-level waste. Commercial reprocessing has been banned in the US since 1977, so almost none of that material gets reused today.
Curio says NuCycle can shrink the leftover waste volume by as much as 97 percent while recovering the useful material. That figure comes from the company, not an independent audit. The technology is still working through lab testing, backed in part by a Department of Energy grant of more than $19 million that Curio and four other companies split in February, with partners including Idaho National Laboratory and Pacific Northwest National Laboratory.
Under the new agreement, Curio would supply recovered material to Newcleo, which would fabricate it into MOX fuel at its planned South Carolina plant. Newcleo says the fuel would work in its own LFR-AS-200 lead-cooled reactor, plus other advanced reactor designs and some light-water reactors already running in the US fleet today. The two companies also plan to keep collaborating on recycling research.
How This Deal Came Together
The Curio agreement didn’t come out of nowhere. It’s the latest step in a yearlong buildout:
- October 2025: Newcleo agrees to jointly develop US fuel-fabrication infrastructure with its reactor partner Oklo, which is racing to line up its own fuel supply elsewhere in the country. Newcleo says it plans to invest up to $2 billion through an affiliated investment vehicle, though it hasn’t detailed specific projects or amounts yet.
- February 2026: The Department of Energy awards Curio and four other companies more than $19 million to keep developing recycling technology, working with Idaho National Laboratory, Pacific Northwest National Laboratory and other partners.
- March 2026: Newcleo starts early talks with the NRC about licensing its LFR-AS-200 reactor and a MOX fuel plant.
- August 2026: Curio signs a separate agreement with NuScale Power and Framatome to study recycled fuel for small modular reactors. Newcleo files a formal Regulatory Engagement Plan with the NRC, laying out how it wants to license the MOX facility under 10 CFR Part 70.
- November 9, 2026: The House of Representatives passes the Nuclear REFUEL Act, which would let reprocessing plants like this one license under the same rules as ordinary fuel facilities instead of a stricter category. It still needs the Senate.
- November 16, 2026: Newcleo and Curio announce their fuel-supply agreement.
Who Benefits and How
This is more an infrastructure story than a consumer one, so don’t expect a lower power bill next year. Here’s who stands to gain, and how, if the plan actually gets built.
Reactor developers get a domestic source of fuel instead of depending entirely on mined and enriched uranium from overseas, chipping away at the fuel-cycle bottleneck the industry has wrestled with all year. That matters for Newcleo’s own reactors, and Curio’s separate deals with NuScale and Framatome suggest the recycled material could eventually feed other companies’ reactors too.
Communities near nuclear sites could see used fuel treated as a resource instead of a permanent liability. Every bit of used fuel from a US commercial reactor is currently classified as high-level waste, with no recycling path. A working NuCycle plant would start chipping away at that stockpile instead of just storing it.
South Carolina could eventually see construction jobs and tax revenue, the way the original MFFF promised two decades ago. Newcleo hasn’t published a jobs estimate for this specific facility, so treat any number you see elsewhere as a guess, not a commitment.
None of that helps anyone soon. Newcleo still needs years of licensing before it fabricates a single fuel pellet.
The Catch
- Newcleo has only filed a pre-application engagement plan with the NRC, not an actual license application. It submitted that plan on August 3, 2026.
- The Nuclear REFUEL Act, which Curio says its technology lines up with, passed the House on November 9 but still needs a Senate vote and a signature before it’s law.
- No one has announced a construction timeline, a cost estimate, or a groundbreaking date for Newcleo’s planned plant.
- The US has never finished a commercial-scale MOX fuel plant. The last attempt, at this same site, ran for more than a decade through rising costs before the government shut it down without producing fuel.
- Curio’s 97 percent waste-reduction figure is the company’s own number. NuCycle is still moving through lab demonstrations, and Curio says it’s targeting a pilot-scale demo by the end of 2027, not sooner.
A signed agreement is not a permit. A permit is not a plant.
Watch for two things over the next year: whether Newcleo actually files that Part 70 license application, and whether the Nuclear REFUEL Act gets a vote in the Senate. Either one will tell you more about this project’s real odds than any press release does.
Sources
- World Nuclear News: Newcleo, Curio team up for recycled nuclear fuel supply (Nov. 16, 2026)
- Nuclear Newswire: Newcleo’s planned Savannah River MOX fuel fabrication plant gets Curio support (Nov. 19, 2026)
- World Nuclear News: Newcleo and Oklo to partner on advanced fuel (Oct. 17, 2025)
- U.S. NRC: Backgrounder on Mixed Oxide Fuel (accessed Nov. 21, 2026)