China’s upgraded Hualong One reactor made news twice in September 2026. On September 7, China General Nuclear (CGN) unveiled “Hualong One 2.0” at a conference in Shenzhen and listed design improvements. Two days later, China National Nuclear Corporation (CNNC) held a mobilization meeting and fired the first excavation blast for Phase II of the Jinqimen plant in Zhejiang province. Phase II is designated as the demonstration of Hualong One 2.0.
How it got from approval to a blast
- December 2023: Jinqimen Phase I is approved. Groundbreaking follows in February 2024.
- August 10, 2025: first concrete for Phase I unit 1. First concrete for unit 2 follows on April 4, 2026.
- July 31, 2026: a State Council executive meeting chaired by Premier Li Qiang approves eight units in total, including two Phase II reactors at Jinqimen as Hualong One 2.0 demonstration projects (World Nuclear News). CGN’s release says Phase III of its Taipingling plant in Guangdong was also named a demonstration project.
- September 7: CGN unveils the 2.0 design in Shenzhen.
- September 9: CNNC fires the first excavation blast for Jinqimen Phase II.
The completed six-unit Jinqimen site would have about 7.2 GWe of capacity and produce roughly 55 TWh a year, according to CNNC. CNNC says that equals half of Ningbo’s 2024 electricity use.
What CGN says changed
CGN’s release, distributed through Kyodo News PR Wire on September 10, lists these changes. It does not say what each figure is measured against.
| Item | Claimed change | Source |
|---|---|---|
| Pipeline length | About 31% shorter | CGN release |
| Process valves | About 25% fewer | CGN release |
| Nuclear island building volume | 21% smaller | CGN release |
| Nuclear island installation volume | About 33% smaller | CGN release |
| Automation operation ratio | Up 66% | CGN release |
| Key equipment localization | 100% | CGN release |
CGN also says it optimized 14 safety features and improved nine key safety indicators. It says operators can go 72 hours after an accident without intervention, and that the plant can sustain itself for seven days. The release gives no steel figure, so no “third less steel” claim holds up. The 33% figure refers to installation volume.
The design builds on the original Hualong One. According to CNNC, 10 Hualong One units operate commercially at home and abroad, and 37 more are approved for construction. CGN credits nearly 100 design optimizations. Niu Wenhua, chief expert of the Hualong One 2.0 program, called the upgrade “a systematic upgrade in quality and efficiency built upon a mature design.”
Why It Matters to You
- Nothing is built yet, so there is no direct benefit today. Excavation has only started for two demonstration units.
- If the claimed cuts in piping, valves and building volume hold up, they could make future plants simpler to build. That is the developer’s claim, not a proven result.
- Electricity customers would feel any effect last. No price data exists, and any savings would depend on construction cost, schedule and financing.
What the numbers leave out
The percentage cuts come from CGN. Neither the release nor press coverage states a baseline, so we can’t confirm what the original Hualong One is being compared to. The 72-hour and seven-day safety claims are developer statements, and we found no independent regulator or lab evaluation. Jinqimen has only started excavation for Phase II, so cost, schedule and construction-time savings are untested. CGN and CNNC both build Hualong One designs, and CGN’s figures should not be read as CNNC’s; we haven’t seen CNNC publish the same list. Finally, the 7.2 GWe and 55 TWh figures describe the full six-unit site, which mixes Phase I and Phase II units.
Quick answers
- Is Hualong One 2.0 under construction? Excavation has begun for two demonstration units at Jinqimen Phase II. No reactor of this version has been built or operated yet.
- Does it use a third less steel? That is not supported. CGN reports about 33% less installation volume in the nuclear island but gives no steel figure.
- Who developed it? CGN unveiled the Hualong One 2.0 branding. CNNC is building the Jinqimen demonstration units. Both companies work on Hualong One designs.
- Will it lower electricity prices? No price data exists yet. Any savings would depend on construction cost, schedule and financing once units are built.
Sources
- World Nuclear News: Groundwork begins for demonstration Hualong One 2.0 units (Sep 14, 2026)
- Kyodo News PR Wire (CGN release): China’s Gen-III+ Advanced Nuclear Power Technology “Hualong One” 2.0 Unveiled to the Global Market (Sep 10, 2026)
