Home » Nuclear Fission » Rooppur Unit 1 Reaches First Criticality in Bangladesh

Rooppur Unit 1 Reaches First Criticality in Bangladesh

Bangladesh’s first nuclear unit reached criticality at 3:34 pm on October 11, 2026, after a safety-valve fault delayed the schedule. Grid power is hoped for in late December, with no…

Trees along a calm riverbank with reflections in the water

Unit 1 of the Rooppur nuclear power plant in Bangladesh achieved its first controlled nuclear reaction, known as criticality, at 3:34 pm on Sunday, October 11, 2026, according to bdnews24. Officials say all key reactor parameters remain within prescribed limits. No electricity has reached the national grid yet.

Getting here took longer than planned. Bangladesh issued an operating licence for unit 1 on April 16, 2026, according to World Nuclear News, and the original target for the next stage was September. Then a fault turned up in a safety valve during testing. Russian specialists helped repair it, and the Dhaka Tribune reports that two safety-valve tests were completed the week before approval.

On Thursday, October 8, the Bangladesh Atomic Energy Regulatory Authority (BAERA) approved the high-pressure test results and issued the licence for the next stage. bdnews24 describes the step as moving unit 1 from stage B-1 to B-2. Separate approvals are required for stages C and D.

“After verification by local and international experts, the licence for the next stage was issued today,” said BAERA chairman Mahmud Hasan.

The plant is two VVER-1200 units of 1,200 MW each, 2,400 MW combined, according to bdnews24 and the Dhaka Tribune. From criticality, bdnews24 says power will be raised gradually to 37 percent to produce turbine steam. Trial grid supply is hoped for in late December, with no firm date, and the Dhaka Tribune says the initial supply could be 300 MW. Trial operation at different output levels is expected to last seven to eight months.

The schedule has slipped before. The project deadline was originally December 2025 and has been extended twice, to June 2028. bdnews24 puts the estimated cost at Tk 1.39 trillion, and says taka depreciation added about Tk 260 billion to it.

Why It Matters to You

For people in Bangladesh, Rooppur is meant to become a large new source of electricity, but nothing reaches the grid yet. Trial supply is only hoped for in late December 2026, and the full 2,400 MW is years of testing and approvals away. No source gives a figure for households served or for bill effects.

What this milestone leaves open

  1. Criticality is a start-up milestone, not electricity. More than 300 tests were done by October 9, and several test stages remain before generation.
  2. The December grid date is a hope voiced by project officials. Reports say no firm date is set.
  3. The 300 MW figure is an initial supply estimate from the Dhaka Tribune. Each unit is designed for 1,200 MW.
  4. The valve fault was repaired with Russian help and cleared by BAERA. There is no independent technical review of the repair.
  5. The project is years behind its original December 2025 deadline.

Quick answers

Is Rooppur producing electricity?

No. Unit 1 reached criticality on October 11, 2026. Further tests and approvals must finish before it supplies the grid.

When will it connect to the grid?

Officials hope for trial supply in late December 2026. No firm date has been set.

Sources

Related Reading